A renowned golfer sought to honor his roots by revitalising his hometown golf club in Northern Ireland. The vision was to establish a comprehensive health and performance centre integrated into the existing clubhouse. Initial designs for the health and performance suite were meticulously crafted. To leave an enduring mark, five cutting-edge simulator bays were incorporated, along with a bar and corporate entertainment area, a modernised restaurant, an expanded kitchen area, and a welcoming reception space. To accommodate these enhancements, the 18th green underwent a strategic relocation.
Our Process
Stage 01 – Design
- Xerspace discuss options
- February 2017 – Initial drafts by architect
- May 2017 – Planning Application submitted
Stage 02 – Planning & Development
- Xerspace discuss options
- June 2017 – Tendering process for gym manufacturer and install
- December 2017 – Tendering process for building contractor
- March 2018 – Planning approved
Stage 03 – Complete
- 1st April 2018 – Builder site set up and preliminaries
- 1st May 2018 – Building commences
- 27th March 2019 – Build complete and handover to club
- 1st April 2019 – Gym and simulator fit-out
- 1st May 2019 – Grand Opening